2 FLEET SHIPLIFT - PEONG TAEK 2016
1. Concrete constrruction of the maintanance area
2. Installation of the rail
3. Construction of the land connectiong section rail
4. Preparing rail welding
5. Rail welding
6. Inspection of the M.T the welding part
7. Grouting construction bottom of the sol plate